Epic Consultants

MIA Building 845/100 Cargo Area Restroom Renovations

Aviation

Owner

Text

Location

Text

Contract

Text

Total Value

Text
The work consisted of complete demolition of the existing restrooms, including plumbing fixtures, lighting, toilet partitions, ducted exhaust fan, toilet accessories, concrete slab, and wall partitions. In order not to disrupt operation of building tenants due to noise, the demolition of the concrete slab was performed at night.
The new work consisted of concrete slab, partitions walls, porcelain wall/floor tile, toilet partition/accessories, lighting, relocation of fire sprinkler heads, hollow metal doors and new trench drain system.